How we plan the hoisting process in industrial roof renovation

We are currently in the execution phase of a roof renovation, and right now we have a crane hoisting 10-meter-long sandwich panels to cover roof pitches at a height of 14 meters.
This is a critical moment. We are executing the renovation of the warehouse roof without halting the client’s activity for a single minute. We maintain production lines at 100%, logistics remain uninterrupted, and the plant stays operational while we work. Achieving this continuity, while minimizing waste and impact, is key for the warehouse to obtain sustainability certifications such as BREEAM In-Use, which we have already secured in several of our projects.
To ensure the client is virtually unaware of our presence, the maneuver is resolved days in advance: studying ground resistance to avoid blocking logistics, setting safety margins for wind, and inspecting every spreader bar at the truck side. If the hoisting is well-planned, the client does not even notice that we are replacing the roof of their factory.
Ensuring this precision in warehouses at full capacity is only possible by combining years of experience in industrial roofing, a highly qualified technical team, and the maximum guarantee of execution for the asset owner.